Timeline
- SHEET
- B5
- REV
- flowfig 0.8.4
- SOURCE
- src/guide.ts
- DATE
- 2026-10-05
This page is the output of npx flowfig docs timeline. Your agent reads the same text.
Read this topic for a roadmap, a plan with dates or a Mermaid gantt. Read the dates from the document.
- Set
"timeline": trueinprops. - Put one labeled group per track in a
columngroup. - Give each item box
fromandto, as YYYY-MM-DD.fromis the first day of the item.tois the last day. - A milestone is a box with
fromonly. - Draw a dependency as an edge from the first item to the dependent item. A dependent item starts after its source ends.
- Set
todayinprops, as YYYY-MM-DD, to stop the today line at that date. Default: the last date of the items. - A Mermaid
ganttsection becomes a track. Each task becomes an item, and eachafterbecomes an edge.